Facility Master Plan Series 1

Budget

$221,390,000

Spent

Missing data

Spending figures are coming from DPSCD

Paid for by

Facility Master Plan

Runs through 2030–31

Projects

17

Latest update (August 2026)

  • Construction continues at Davis Aerospace, Pershing and Paul Robeson Malcolm X Academy.
  • Demolition activities have commenced at Golightly CTC for the new Carstens Elementary-Middle School.
  • Renovation work at Denby for the Graphics Arts space has been completed.

Scope of work

  • New Buildings
  • Building Demolitions
  • City Airport Renovations
  • School Relocations
  • CTE Space Renovations
  • CTE Relocations
  • Athletic Complex
  • Phase Out

Where projects stand

Not started
3
Planning
0
Procurement
0
Design
3
Construction
5
Closeout
3
Other
3

17 projects