Budget

$1,208,765

Spent

Missing data

Spending figures are coming from DPSCD

Paid for by

Surplus funding from the board

Approved by the board each year

Projects

28

Latest update (August 2026)

  • February Board Budget Amendment approved funding for these projects.

Scope of work

  • Play Area Fencing
  • Parking Lot Fencing
  • Gates
  • Athletic Field Fencing

Where projects stand

Not started
28
Planning
0
Procurement
0
Design
0
Construction
0
Closeout
0
Other
0

28 projects