Preview for DPSCD review. Not public yet. Anything marked “Missing data” is information we still need from the District.
All programs

Surplus funding from the board

Coleman A. Young and F.L.I.C.S. Building Upgrades

Budget

$15,400,000

Spent

Missing data

Spending figures are coming from DPSCD

Paid for by

Surplus funding from the board

Approved by the board each year

Projects

12

Latest update (August 2026)

  • CAY scope of work is substantially complete. Punchlist items remain.
  • FLICS roofing and unit ventilator work substantially complete. Punchlist items remain.
  • FLICS elevator work to be completed November 2026 through January 2027.
  • FLICS boiler installation and commissioning on track for October completion.

Scope of work

  • Roofing
  • HVAC and Controls
  • Elevator Modernization
  • Restroom Renovations
  • Concrete Replacement
  • Doors and Windows
  • Ceilings and Lighting

Where projects stand

Not started
0
Planning
0
Procurement
0
Design
0
Construction
4
Closeout
8
Other
0

12 projects